Project Grade 9 Careers & CTE

Haldreth's PFAS Treatment Upgrade: A Utility Staffing Plan

A five-session grade 9 careers project in which teams staff a fictional district's new PFAS treatment building against licensing rules and a fixed payroll budget.

Objectives

  1. Students will convert the added tasks of a treatment upgrade into weekly labor hours by role.
  2. Students will build a staffing plan that meets stated licensing coverage rules within a payroll limit.
  3. Students will justify a staffing choice in a memo that names the cost each option places on staff and on ratepayers.

Vocabulary

Granular activated carbon
Small black grains of specially treated carbon that grab contaminants as water flows through them. Utilities use big tanks of it to remove PFAS, bad tastes, and odors.
Confined space entry
Special safety rules workers follow before going into enclosed spaces like tanks, vaults, and manholes. The air is tested and a trained team stands by, because these spaces can be dangerous.

Also: operator license class, creditable experience, payroll burden, coverage

Teacher overview

The Haldreth Water District, a fictional utility used throughout this project, has been told to add treatment for PFAS, and the district now has to find people qualified to run it. Over five sessions, teams convert the new building's tasks into labor hours, build a staffing plan that satisfies the district's license-coverage rule and payroll limit, and defend the plan in a memo to the district board. A teaching note before you begin: students usually assume that a staffing gap can be closed by posting a job and hiring, which is why the licensing timeline in the brief matters. A Class III license takes two years of documented experience to earn, so a district that needs a Class III operator next year has to recruit or promote someone who already holds the license and backfill the position behind that person. EPA set the maximum contaminant level for PFOA and PFOS at 4.0 parts per trillion each in its April 2024 rule, with compliance required by April 2029. In May 2026 the agency proposed letting eligible systems apply for a two-year exemption, to April 2031; the proposal was not final as of September 2026 and would not change the 4.0 ppt limits, so students should treat the deadline as a rule still in motion rather than a settled date.

Rubric

Criterion Emerging Developing Proficient Advanced
Coverage rule The plan leaves hours when no licensed Class III operator is on site The plan claims coverage but the table does not show how every hour is filled The table shows a licensed Class III operator on site for all hours the plant produces water The table shows full coverage and identifies which position absorbs an unplanned absence
Payroll limit Total payroll exceeds the approved amount, or benefits are left out Benefits are applied inconsistently, or the total is stated without the arithmetic Total payroll including the 32 percent benefits load is inside the approved amount and is shown line by line Total payroll is inside the limit, shown line by line, with a stated margin held back for overtime
Credential matching Tasks are assigned to roles that may not legally perform them Most tasks match the right credential, with one or two mismatches Every task is assigned to a role holding the required license or certification Every task matches, and the plan explains how the district keeps a second certified person available for confined space work
Memo and reasoning The memo restates the plan without reasons The memo gives reasons but does not compare the two options The memo compares both options and names who bears the cost of the chosen one The memo compares both options, names who bears the cost, and anticipates a board question with evidence from the table

Differentiation

Support

Give these teams the Session 1 table already filled in, so the work starts at the staffing decision rather than the arithmetic. Provide a worked example of the benefits calculation using one role from the fictional wage list, showing the base wage, the 32 percent addition, and the total. Allow the memo to be written as five labeled paragraphs with a sentence starter for each.

Extension

Ask these teams to plan for the licensing timeline rather than only the startup date. Given that a Class III license requires 24 months of documented experience, have them show which current employee moves into the new building, who backfills that person, and when an operator in training hired now becomes eligible to sit for the exam. EPA has reported that roughly one-third of the water workforce becomes retirement-eligible within the next decade, so ask teams to state what their plan would look like if one Class III operator retired in the same year the building opens.

ELL supports

Pre-teach license class, creditable experience, coverage, payroll burden, and confined space using a labeled diagram of the fictional Haldreth plant with each role placed where it works. Provide the memo as a frame: the district needs, our plan adds, this meets the rule because, and the cost of this choice falls on. Allow the staffing table to carry short phrases rather than full sentences.

Extensions

Invite a licensed operator or a utility human resources staff member to review two teams' plans and describe how their own agency fills a position that requires a license. If a visitor is not available, have teams compare their plans against a real job posting from any nearby water utility, listing which credentials the posting requires and which of the fictional Haldreth roles it most resembles.