Math problem set Grade 6 Careers & CTE

Hartsmoor Valve Crew: A Week of Unit Rates

A grade 6 careers problem set on a valve maintenance crew's week, covering valves-per-hour unit rates, percent of a program finished, and decimal multiplication.

Objectives

  1. Students will calculate a valves-per-hour unit rate for each day of a crew's week.
  2. Students will find what percent of a maintenance program has been completed.
  3. Students will multiply a decimal number of minutes by a count of valves.

Vocabulary

Valve
A valve is a device in a pipe that operators can open or close to control where water flows. Valves let crews shut off one street for repairs without turning off the whole town.
Distribution system
A distribution system is the network of pipes, pumps, valves, and storage tanks that carries treated water from a treatment plant to homes, schools, and businesses. Most of it is buried underground beneath streets.

Also: exercising a valve, unit rate, percent

Teacher overview

Every problem in this set comes from one week with the valve crew at the fictional Hartsmoor Water Department, and the problems follow the order the crew's own records are filled in. Students move from a single day's rate, to the week's total, to the share of a multi-year program that has been finished. One misconception runs through the whole set and is worth naming first. Students often compare the raw daily totals and decide that the day with the most valves was the crew's fastest day, which ignores the hours worked. Tuesday shows why that reading fails, because its 21 valves is close to Monday's 24 while the crew worked an extra hour to reach it.

Answer Key

  1. Answer: 4 valves per hour.
    A unit rate divides the count by the time. 24 valves divided by 6 hours equals 4 valves per hour.
  2. Answer: 3 valves per hour.
    21 valves divided by 7 hours equals 3 valves per hour. Tuesday's total of 21 is close to Monday's 24, yet the crew needed an extra hour, so its rate is lower.
  3. Answer: 5 valves per hour.
    30 valves divided by 6 hours equals 5 valves per hour, the crew's best rate of the week.
  4. Answer: 120 valves.
    24 plus 21 equals 45. 45 plus 30 equals 75. 75 plus 18 equals 93. 93 plus 27 equals 120 valves.
  5. Answer: 10 percent.
    12 divided by 120 equals 0.1, and 0.1 written as a percent is 10 percent.
  6. Answer: 10 weeks.
    1,200 valves divided by 120 valves per week equals 10 weeks.
  7. Answer: 30 percent.
    3 weeks times 120 valves equals 360 valves. 360 divided by 1,200 equals 0.3, which is 30 percent.
  8. Answer: 75 minutes.
    30 valves times 2.5 minutes equals 75 minutes of turning.
  9. Answer: 40 valves per worker.
    120 valves divided by 3 workers equals 40 valves for each worker.

Differentiation

Support

Give these students the fictional Hartsmoor table with a third column headed "Valves per hour" so the division in problems 1 through 3 has a place to go, and print problem 5 with the fraction already written as 12 over 120. Assign problems 1 through 6 only, and allow a calculator throughout.

Extension

Ask students to find the crew's rate for Thursday and Friday, rank all five days from fastest to slowest, and write a short paragraph explaining why the fictional Hartsmoor supervisor should look at rates rather than daily totals when planning next week's route.

ELL supports

Pre-teach "valve," "exercise a valve," and "unit rate" with a simple drawing of a valve under a street beside a wrench. Provide the sentence frame "On ____ the crew did ____ valves in ____ hours, so the rate was ____ valves per hour." Allow students to say each answer aloud before writing it.

Extensions

Have students plan a two-year schedule for the fictional Hartsmoor system so that every one of the 1,200 valves is exercised twice, stating how many valves a week that takes and whether the current crew can reach it. Students then write two sentences explaining how many weeks of the two years that schedule would take the current crew and what the crew could do with the remaining time.