Project Grade 11 Engineering & Design

Ledgemont Wastewater Plant: A Phosphorus Removal Upgrade

A grade 11 engineering project where teams design a phosphorus removal upgrade for a fictional wastewater plant, sizing a chemical feed system within a budget.

Objectives

  1. Students will calculate the daily phosphorus load a plant must remove to meet a permit limit.
  2. Students will size a chemical feed and storage system and test it against a footprint and a budget.
  3. Students will justify one treatment recommendation in a written memo to a utility board.

Vocabulary

Key words: total phosphorus, effluent permit limit, chemical precipitation, biological phosphorus removal, pounds formula

Teacher overview

Phosphorus is a nutrient that plants need, yet too much of it in a river feeds algae blooms that strip oxygen from the water. Secondary treatment rules set limits on BOD and TSS, and many states add a separate phosphorus limit to a plant's discharge permit when the receiving stream is already stressed. In this five-session project, teams design a phosphorus removal upgrade for the fictional Ledgemont wastewater plant, size the chemical feed and storage it would need, and defend the choice in a memo and a short presentation to a fictional utility board. The order of the work matters in this project, because teams need the load calculation from Milestone 1 in hand before they size the feed system and compare the two technologies, and the $250,000 capital budget is what separates the two options.

Rubric

Criterion Emerging Developing Proficient Advanced
Load and removal calculation Loads are missing or carry no units Loads are calculated but the required removal or the efficiency is wrong All four load values and the removal efficiency are correct with units shown Values are correct, units are shown at every step, and the team states how a wet-weather flow increase would change the load
Feed and storage sizing Feed rate is missing or uses the wrong formula Feed rate is found but the solution volume or the 14-day storage is not completed Feed rate, daily solution volume, tank volume, and tank dimensions are correct and fit the building floor Sizing is correct and the team explains why the chosen tank diameter is a better fit for the room than an alternative they tested
Meeting the stated constraints The design misses the permit limit, the footprint, or the budget without comment The design meets some constraints, and the others are not checked The memo shows the design meets the permit limit, the 14-day storage, the footprint, and the $250,000 budget All constraints are met and the team quantifies the margin it holds on cost and on storage days
Trade-off analysis and memo No comparison is made between the two options The two options are described but not scored on stated criteria The trade-off table scores both options on all four criteria, and the memo defends one choice with the capital and annual costs it calculated The memo defends the choice with numbers, states plainly that the biological option cannot meet the capital budget, names one honest weakness of the recommendation, and proposes how the district could monitor it

Differentiation

Support

Give these teams the Milestone 1 load calculation already worked, so their five sessions center on the sizing and the trade-off analysis rather than on the opening arithmetic. Provide a partly filled sizing table with the conversion factors printed in each column header, and a process flow diagram with the unit processes drawn but unlabeled.

Extension

Ask teams to recalculate the ferric chloride feed rate for a fictional wet-weather day when plant flow rises to 6.5 MGD while the influent phosphorus concentration falls to 4.0 mg/L, then decide whether the 14-day storage tank they sized still holds enough chemical. Have them state, in one paragraph, whether a plant should size chemical storage on average flow or peak flow.

ELL supports

Pre-teach "influent," "effluent," "dose," and "permit limit" with a labeled cross-section of the fictional plant showing water entering on the left and leaving on the right. Provide a memo template with headings and sentence frames, such as "We recommend ___ because it removes ___ pounds per day of phosphorus at a capital cost of ___." Allow the trade-off table to be scored with symbols before the team writes the sentences.

Extensions

Teams that finish early can research how the fictional district might recover phosphorus rather than discard it, since phosphorus captured from wastewater can be processed into fertilizer. Ask them to add one paragraph to the memo describing what recovery would require and why a small district might still choose disposal.