Worksheet Grade 12 Engineering & Design

Alder Flats Well Field: Drawdown and Specific-Capacity Worksheet

A grade 12 engineering worksheet where students compute well drawdown, specific capacity, and daily yield for two wells in a fictional well field, then compare them.

Objectives

  1. Students will calculate well drawdown and specific capacity from static and pumping water levels.
  2. Students will compare two wells and interpret a change in specific capacity over time.

Vocabulary

Drawdown
Drawdown is how far the water level in a well drops when a pump pulls water out. The harder and longer you pump, the bigger the drawdown gets.

Also: static water level, pumping water level, specific capacity, yield

Teacher overview

The fictional Alder Flats well field pumps groundwater from two wells. Operators track each well's drawdown, which is how far the water level drops while the pump runs, and its specific capacity, which is the yield for each foot of drawdown. This worksheet has students compute both values, compare the two wells, and interpret what a falling specific capacity means over time.

Answer Key

  1. Answer: 55 feet.
    Drawdown = 95 feet - 40 feet = 55 feet.
  2. Answer: 5.45 gpm per foot.
    Specific capacity = 300 gpm / 55 feet = 5.4545, which rounds to 5.45 gpm per foot.
  3. Answer: 40 feet.
    Drawdown = 78 feet - 38 feet = 40 feet.
  4. Answer: 6.5 gpm per foot.
    Specific capacity = 260 gpm / 40 feet = 6.5 gpm per foot.
  5. Answer: Well 2.
    Well 2's specific capacity of 6.5 gpm per foot is higher than Well 1's 5.45 gpm per foot.
  6. Answer: It is more productive.
    A higher specific capacity means the well produces more water for each foot the level drops, so it is more efficient and productive for the same drawdown.
  7. Answer: 324,000 gallons.
    300 gpm x 60 minutes x 18 hours = 324,000 gallons.
  8. Answer: 0.324 MGD.
    324,000 gallons / 1,000,000 = 0.324 MGD.
  9. Answer: 214.5 gpm.
    Yield = specific capacity x drawdown = 3.9 gpm per foot x 55 feet = 214.5 gpm. The lower specific capacity means the well now produces less water at the same drawdown.
  10. Answer: Clogging; rehabilitate the well.
    Accept any sound pair. A common cause is mineral scale, sand, or bacterial buildup clogging the well screen. A common action is to rehabilitate or redevelop the well to restore its capacity.

Differentiation

Support

Provide a labeled cross-section of a well showing the static level, the pumping level, and the drawdown between them. Work item 1 as a class example, and give the two formulas on a printed card.

Extension

Ask students to find the difference in daily yield between Well 1 and Well 2 if both run 18 hours at their listed rates, then explain why Well 1 delivers more water each day even though Well 2 has the higher specific capacity, and how a daily difference of that size adds up over a year.

ELL supports

Pre-teach "static," "pumping level," "drawdown," and "yield" with the labeled cross-section and a home-language gloss where possible. Allow students to answer items 6 and 10 with a labeled sketch plus a short phrase rather than full sentences.