Project Grade 9 Engineering & Design

Cravenmoor Ridge After the Fire: A Backup Water Supply Design

A five-session grade 9 project where students design a backup supply for a fictional mountain water district under a fixed budget and a minimum pressure requirement.

Objectives

  1. Students will state measurable criteria and constraints for an emergency water supply project.
  2. Students will calculate a district's daily demand, three-day storage need, and fire flow volume.
  3. Students will score competing options in a weighted trade-off matrix and defend one recommendation.

Vocabulary

Key words: criterion, constraint, fire flow, trade-off matrix, interconnection

Teacher overview

The driving question of this project is how a small mountain utility should spend a limited grant to keep water flowing after a wildfire. Cravenmoor Ridge is a fictional water district whose watershed burned last summer, leaving its creek intake fouled with ash after every rainstorm and its single power feed exposed to shutoffs on windy days. Students take the district's stated budget and performance requirements, size the demand and storage the system must cover, evaluate three competing options, and deliver a written proposal and a presentation to the fictional district board. The work follows the same path as a consulting engineer's resilience study, which ends in a recommendation supported by numbers.

Rubric

Criteria and constraints (Milestone 1)

  • Level 4: Every criterion states a quantity, a unit, and a verification method; every constraint names its source; two additional requirements are proposed with sound justification.
  • Level 3: Criteria and constraints are correctly separated and mostly measurable; at least one additional requirement is proposed.
  • Level 2: The two categories are mixed in places, or several criteria state goals without quantities.
  • Level 1: The memo restates the board's requirements without sorting or quantifying them.

Quantitative analysis (Milestone 2)

  • Level 4: Demand, three-day volume, fire flow volume, and shortfall are all correct, with units carried through every conversion and a stated check on the arithmetic.
  • Level 3: All four quantities are present and the method is correct, with one arithmetic or unit slip.
  • Level 2: Some quantities are missing or the conversions drop units, so the shortfall cannot be traced.
  • Level 1: Numbers appear without visible calculation, or the demand figure does not follow from the connection count.

Trade-off evaluation (Milestones 3 and 4)

  • Level 4: The matrix scores every option and affordable pair on at least four criteria, the weights are defended in writing, and the recommendation names the strongest counterargument.
  • Level 3: The matrix is complete and the recommendation follows from the scores, but the weights are asserted rather than defended.
  • Level 2: Options are compared informally, or the recommendation does not follow from the team's own scoring.
  • Level 1: One option is favored with no comparison against the budget or the requirements.

Proposal and presentation (Milestone 5)

  • Level 4: The proposal is organized, every performance claim cites a number from the calculations, and the team answers the challenge question by returning to its evidence.
  • Level 3: The proposal covers all required sections and the presentation is clear, with one or two claims left unsupported.
  • Level 2: Sections are missing or the presentation restates the brief without adding the team's analysis.
  • Level 1: The deliverable is incomplete, or the recommendation is stated without supporting work.

Differentiation

Support

Give these students the Milestone 2 calculation sheet as a partly completed frame with the demand row filled in for this fictional district, so the remaining work is the three-day volume and the fire flow volume. Provide the trade-off matrix as a printed grid with the four criteria already listed and the weights supplied, leaving only the scoring to the team. Allow the presentation to be delivered from a script.

Extension

Ask these teams to add a fourth option of their own design, such as a demand reduction program, a raw water storage pond, or a mobile treatment trailer, and to price it from research they document. Then have them test how sensitive their recommendation is by changing one weight in the matrix and reporting whether the winner changes. Teams can also model what happens to the fictional district's three-day requirement if connections grow by fifteen percent over ten years.

ELL supports

Pre-teach criterion, constraint, fire flow, interconnection, and trade-off with a one-page picture glossary showing the tank, the well, the intake, and the interconnection pipe. Provide sentence frames for the memo, such as "This is a criterion because it can be measured in ___" and "This is a constraint because the design cannot ___." Allow the board presentation to be given in pairs so one student handles the numbers and the other handles the recommendation.

Extensions

Have teams write the one-page public notice the fictional Cravenmoor Ridge district would mail to customers explaining what the project buys them and what it does not. Ask them to state plainly which failure the project protects against and which failures remain, because a notice that overstates what the project can do leaves customers expecting protection the district cannot provide. Teams can then trade notices and mark any sentence a worried customer might read as a promise the district cannot keep.