Project Grade 9 Math

Aldergate's Aging Pipes: A Water-Main Break Trend and Budget Project

A grade 9 project where students model a fictional town's rising water-main break trend and propose a pipe-replacement plan within budget and construction limits.

Objectives

  1. Students will graph a multi-year data trend with labeled, scaled axes and write a linear equation modeling that trend.
  2. Students will evaluate a proposed plan against two stated constraints, a budget limit and a construction-capacity limit, and identify which constraint is binding.

Vocabulary

Key words: trend, linear model, constraint, binding constraint

Teacher overview

Nationally, the ASCE 2025 Infrastructure Report Card gave United States drinking water a grade of C-, and a water main breaks somewhere in the country roughly every two minutes, a reminder of how widespread aging pipe networks have become. This project brings that national picture down to the scale of a single fictional town, Aldergate, where student teams act as engineering interns analyzing four years of water-main break records, building a linear model of the trend, and proposing which segments of pipe to replace first within a fixed budget and a real construction limit. The final deliverable is a written recommendation with a labeled graph, presented to the class in the role of Aldergate's town council.

Rubric

Criterion Emerging Developing Proficient Advanced
Trend model Graph or equation is missing, mislabeled, or does not match the data Graph and equation are present but axes are not clearly labeled or scaled, or the equation does not match the data pattern Graph has labeled, scaled axes and the equation B(y) = 3y + 9 correctly matches the four years of data Graph and equation are correct and the team also correctly projects Year 5 and Year 8 break counts using the model
Constraint analysis Recommendation does not check the budget or construction limits Recommendation checks one constraint (budget or construction capacity) but not both Recommendation checks both constraints and correctly identifies the construction limit as binding Recommendation checks both constraints, correctly identifies the binding constraint, and explains in plain language why the less restrictive constraint (budget) does not fully determine the plan
Presentation & recommendation Recommendation is incomplete or difficult to follow Recommendation states a plan but does not clearly connect it to the projected break reduction Recommendation clearly states the miles replaced, total cost, and projected break reduction, tied to the team's model Recommendation clearly connects the model, both constraints, and the projected outcome, and anticipates a likely question from the town council, such as what happens in future years if funding stays the same

Differentiation

Support

Provide the completed equation B(y) = 3y + 9 already derived for Session 1, so teams can spend their time interpreting and projecting with it rather than deriving it from the data. Provide a partially completed constraint table for Session 2 with the budget-miles calculation already worked out, leaving only the construction-limit comparison for teams to complete.

Extension

Ask teams to calculate, using their model, in what year Aldergate's break count would first exceed 30 if no replacement work is ever done, and to propose a multi-year replacement schedule (still respecting the 2-mile-per-year construction limit) that would keep the break count from ever reaching that level.

ELL supports

Provide a labeled diagram showing a pipe segment, a road closure sign, and a cost tag, illustrating the connection between "one mile replaced," "one road closed," and "$50,000 spent" in this fictional town's project, before Session 2's constraint work. Allow the written recommendation in Session 4 to include labeled diagrams and a data table alongside shorter sentences rather than full paragraphs.