Project Grade 10 Science

Ostlin's Drought Plan: A Spreadsheet Water Budget

A five-session grade 10 project where teams build a monthly spreadsheet water budget for a growing town, stress-test it, and choose a 15-year drought plan.

Objectives

  1. Students will build a monthly water budget that tracks reservoir storage as river supply and town demand change through the year.
  2. Students will project demand forward with a growth rate and find the first year the reservoir falls below its drought reserve.
  3. Students will choose measures that fit a stated budget and protect the drought reserve under dry-year and high-growth tests.

Vocabulary

Water budget
A water budget is a way of tracking all the water coming into an area, like rain and snowmelt, against all the water leaving it, like evaporation and streamflow. Scientists use water budgets to see whether a watershed or aquifer is gaining or losing water over time.
Acre-foot
The amount of water it takes to cover one acre of land, about the size of a football field, one foot deep. Western states use acre-feet to measure large amounts of water.

Also: drought reserve, peak demand, reclaimed water

Teacher overview

A growing town will eventually ask for more water than its river and reservoir can deliver through a dry summer, and its planners have to work out which year that happens and what to build first. Over five sessions, teams build a month-by-month spreadsheet water budget for the fictional town of Ostlin, project it fifteen years forward, and test it against two dry years and faster growth. They then choose a package of conservation and supply measures that fits a fixed capital budget, and the final deliverable is a written plan and a short presentation to a fictional water board, which votes on the packages.

Rubric

Criterion Emerging Developing Proficient Advanced
Model construction Table is incomplete or the supply and demand columns do not connect to storage Model balances one month but formulas are entered by hand rather than linked, or storage is allowed to rise above full capacity Model links demand, river supply, and reservoir storage across all twelve months and fifteen years, caps storage at full capacity, and matches the Year 0 values in the teacher reference Model is fully linked, clearly labeled, and lets the growth rate, dry years, or any measure be changed without rebuilding the sheet
Use of constraints Package ignores the budget cap or the drought reserve Package meets one constraint but not the other Package meets the budget cap and keeps the reservoir at or above 300 acre-feet in every modeled month, including the two dry years Package meets both constraints with a stated margin and the plan explains the trade-off behind each measure chosen
Stress testing No stress test attempted One stress test run but results not interpreted Both stress tests run and the failing constraint, month, and year identified Both stress tests run, the failing constraint identified, and the package revised with a stated reason and a cost comparison
Written plan and presentation Plan omits the cost or the shortfall year Plan reports results without explaining the reasoning Plan names measures, cost, the no-action shortfall year, and the reservoir's lowest storage under the plan clearly Plan does all of that and answers the board's question with evidence from the model

Teacher reference

Use these figures to check team models. Values are rounded to one decimal place at the end of each calculation, so a team that rounds monthly values first may differ by a few tenths of an acre-foot. One million gallons is 1,000,000 ÷ 325,851 = 3.0689 acre-feet.

Year 0 baseline (Session 1).

Month Change in storage (MG) Change in storage (acre-feet) End-of-month storage (acre-feet)
January +136.4 +418.6 1,400.0 (full)
February +123.2 +378.1 1,400.0 (full)
March +133.3 +409.1 1,400.0 (full)
April +123.0 +377.5 1,400.0 (full)
May +31.0 +95.1 1,400.0 (full)
June −42.0 −128.9 1,271.1
July −86.8 −266.4 1,004.7
August −93.0 −285.4 719.3
September −69.0 −211.8 507.6
October +27.9 +85.6 593.2
November +126.0 +386.7 979.9
December +136.4 +418.6 1,398.5

The August draw is (5.0 − 2.0) × 31 = 93.0 million gallons, and 93,000,000 ÷ 325,851 = 285.4 acre-feet.

Answer: 285.4 acre-feet drawn from the reservoir in August of Year 0.

The June-through-September draw is 42.0 + 86.8 + 93.0 + 69.0 = 290.8 million gallons, which is 892.4 acre-feet, so storage bottoms out at 1,400 − 892.4 = 507.6 acre-feet at the end of September. The reservoir refills in January.

Answer: 507.6 acre-feet, the lowest storage of Year 0, at the end of September.

Fifteen-year projection with no action (Session 2). The January-through-May surplus refills the reservoir to 1,400 acre-feet every normal year, so each year's lowest point is the end of September. Because the river permit does not grow, the June-through-September draw in Year n is (558.8 × 1.012^n − 268.0) million gallons, where 558.8 is the four-month Year 0 demand total and 268.0 is the four-month river total.

Year Growth factor Lowest storage (acre-feet) Year Growth factor Lowest storage (acre-feet)
1 1.0120 487.0 9 1.1133 313.2
2 1.0241 466.2 10 1.1267 290.3
3 1.0364 445.1 11 1.1402 267.1
4 1.0489 423.8 12 1.1539 243.7
5 1.0615 402.2 13 1.1677 219.9
6 1.0742 380.3 14 1.1818 195.9
7 1.0871 358.2 15 1.1959 171.6
8 1.1001 335.9

Answer: Year 10, when end-of-September storage falls to 290.3 acre-feet, below the 300 acre-foot reserve.

In Year 15 the August draw alone is (5.0 × 1.1959 − 2.0) × 31 = 123.4 million gallons, or 378.6 acre-feet. With no action, the dry-year test empties the reservoir in October of Year 14 (the formula gives −149.4 acre-feet, which means the reservoir would run dry), and 2.4 percent growth moves the first shortfall to Year 5, at 291.7 acre-feet.

Measure effects (Session 3). Over June through September (122 days), each 1.00 MGD of reduced demand or added supply saves 122 million gallons, or 374.4 acre-feet. The tiered rates save 112.3 acre-feet, the timer rebates 18.7, the turf rebates 74.9, leak repair 93.6, reclaimed water 168.5, and the new well 337.0. These savings add only while every one of the four months is still a draw month, which holds for any package whose combined effect is 1.40 MGD or less. A larger package can turn June into a surplus month, and because the reservoir is full on June 1, that surplus is left in the river.

Sample package A (passes the normal and dry-year tests, fails the growth test). Tiered rates, turf rebates, and the new well cost $120,000 + $600,000 + $3,100,000 = $3,820,000 and have a combined effect of 0.30 + 0.20 + 0.90 = 1.40 MGD.

Answer: $3,820,000 total capital cost for package A.

Answer: 695.7 acre-feet, package A's lowest storage at 1.2 percent growth, at the end of September in Year 15.

Answer: 341.4 acre-feet, package A's lowest storage with Years 14 and 15 dry, at the end of October in Year 15 (Year 14 bottoms out at 374.8 acre-feet in October).

Answer: At 2.4 percent growth, package A first falls below the reserve at the end of October in Year 14, at 286.2 acre-feet, and its lowest storage is 207.5 acre-feet at the end of October in Year 15, so the drought reserve is the constraint that fails.

Sample package B (revised from A, passes all three tests). Adding dredging raises the total to $3,820,000 + $1,800,000 = $5,620,000, which is $380,000 under the cap.

Answer: $5,620,000 total capital cost for package B.

Answer: 875.7 acre-feet at 1.2 percent growth (end of September, Year 15), 521.4 acre-feet with Years 14 and 15 dry (end of October, Year 15), and 387.5 acre-feet at 2.4 percent growth (end of October, Year 15).

Common misjudgment. Tiered rates and turf rebates alone cost $720,000 and keep the reservoir above the reserve in every normal year (lowest 358.8 acre-feet in Year 15), yet in the dry-year test storage falls to 37.8 acre-feet in October of Year 14, and the reservoir runs dry in Year 15. A team that stops after the normal-year run will believe this cheaper package is enough. Other passing packages exist, such as tiered rates, leak repair, the new well, and dredging for $5,870,000, so judge each team's package by its own model output against this reference.

Differentiation

Support

Give these teams the Year 0 baseline table already built in a spreadsheet, with the formulas for change in storage and end-of-month storage entered in the January row as a model, so their work begins at the projection step. Provide the acre-foot conversion worked once for August, and allow them to choose from a shortened price sheet of four measures: tiered rates, turf rebates, the new well, and dredging. Teams working on paper can record only the four draw months for each year, since the reservoir refills to full by June in every normal year.

Extension

Ask teams to add a column that estimates how each measure changes the average household bill, using a cost-per-customer figure you supply, and to explain which package a household on a fixed income would prefer. Have them name the measure with the widest gap between cost and public support. A second option is to phase the spending, building the well in Year 6 instead of Year 1, and to find the latest year each measure could start without breaking the reserve.

ELL supports

Pre-teach "budget," "reserve," "shortfall," "permit," and "acre-foot" with a labeled diagram of a reservoir showing the usable storage, the full line, and the reserve at the bottom. Provide a labeled spreadsheet template with column headings already written, and allow teams to plan in their home languages before drafting.