Project Grade 10 Careers & CTE

Draythorne's Pump Overhaul Plan: A Maintenance Planner Project

A grade 10 careers project where teams act as maintenance planners, ranking seven pumps by cost per added service year and scheduling a year of overhauls.

Objectives

  1. Students will rank capital repair options by cost per added year of service rather than by equipment age.
  2. Students will represent a maintenance budget and a labor limit as inequalities and test candidate packages against both.
  3. Students will build a work-order schedule that respects peak-season, redundancy, and operator certification requirements.

Vocabulary

Asset management
The practice of keeping track of everything a utility owns, like pipes and pumps, and planning the smartest times to fix or replace each one. It helps spend repair money wisely.

Also: work order, wire-to-water efficiency, overhaul, criticality, crew-hour

Teacher overview

A maintenance planner at a water utility decides, every budget year, which pumps get rebuilt, which get replaced, and which run one more year. Over four sessions, teams take that role at the fictional Draythorne Water Works, where seven pumps compete for one repair budget and one small crew. The misconception this project is built to correct is the belief that the oldest pump is always the one to fix first, because planners rank work by the cost of each added year of service and by how badly the system needs that pump, so a thirty-one-year-old pump can reasonably wait while a newer one is rebuilt. Teams deliver a written maintenance plan and a briefing to the utility's plant manager.

Rubric

Criterion Emerging Developing Proficient Advanced
Cost-per-year ranking The ranking is missing or simply lists pumps by age Some cost-per-added-year figures are computed, yet the ranking is incomplete or contains arithmetic errors All seven pumps are ranked correctly by cost per added year of service The ranking is correct and the team explains where criticality should override the pure cost ranking
Constraint modeling No inequality is written and totals are not checked An inequality is written for one constraint only, or totals are checked informally Both inequalities are written correctly and each candidate package is tested against both Both inequalities are written correctly, both packages are tested, and the team identifies which constraint is binding
Schedule and certification staffing The calendar is missing or ignores the stated restrictions The calendar places work orders yet violates the peak-season rule or the one-pump-out rule The calendar honors the peak-season, redundancy, and mechanic-availability requirements The calendar honors every requirement and leaves a stated reserve of crew-hours for emergency repairs
Memo and briefing The memo states a choice with no supporting figures The memo reports the chosen package yet omits the table, the inequalities, or the calendar The memo contains every required element and defends one pump left alone The memo contains every element, defends the deferral, and answers the challenge question with specific figures

Differentiation

Support

Give teams the cost-per-added-year column already computed for the first three pumps, so they can see the pattern before finishing the remaining four rows. Provide a calendar grid with the July and August cells already shaded, along with a worked example of one inequality built from two pumps.

Extension

Ask teams to test whether replacing a single pump outright, rather than rebuilding two, produces a lower cost per added year over a fifteen-year horizon, and to state what information they would need from the manufacturer to answer that question with confidence.

ELL supports

Pre-teach the terms overhaul, work order, criticality, and crew-hour with a labeled diagram of a pump and motor set. Allow the memo's defense paragraph to be delivered orally to the teacher before it is written, and provide a sentence frame for the viability verdict.

Extensions

Invite a maintenance planner or a public works supervisor to review two teams' calendars and describe how their own agency sets repair priorities. Teams can also convert their chosen package into a bar chart of spending by station, then discuss whether the station with the oldest equipment should always receive the largest share of a repair budget.