A Sampling Pole for Thrushwater Creek: A Grade 4 Design Project

A four-session grade 4 project in which teams build and refine a pole that dips a water sample from four feet out over a creek without spilling or tipping.

Objectives

  1. Students will write a problem statement listing the sampling pole's targets and limits.
  2. Students will build a pole that reaches four feet and returns a measured sample.
  3. Students will change one part at a time to fix a failure they recorded.
  4. Students will present a final design with a budget sheet and a test result.

Vocabulary

Key words: sample, prototype, failure point, fair test, reach

Teacher overview

Teams design, build, and refine a pole that dips a cup of creek water from four feet away and brings it back upright and nearly full. The client is a fictional volunteer group that has been wading into the water to collect its monthly sample, which is slow work and risky on an icy bank. The targets and limits in the brief follow from that job. Testing happens indoors with a taped standing line and a tub of water, and the session 3 rule of changing one part at a time is what separates this from a craft project. The final deliverable is a working pole, a test sheet, a budget sheet, and a short demonstration.

Rubric

Criterion Emerging Developing Proficient Advanced
Problem statement Lists fewer than four of the seven targets and limits Lists most targets but leaves out the token limit or the backpack limit Lists all four targets and all three limits in the team's own words Lists all seven and adds a target the brief left out, such as working with cold hands
Pole performance Pole does not reach 4 feet or returns almost no water Pole reaches 4 feet but the cup tips or returns less than 3/4 cup Pole reaches 4 feet and returns at least 3/4 cup upright on at least two of three tries Meets every target on all three tries, and the team names the design choice that made it steady
Refining from tests No failure point is recorded, or several parts change at once A failure point is recorded, but more than one part changes between test sets Exactly one part changes between test sets, and the team compares the two sets of rows One part changes, the team explains why that part was the failure, and the test rows show the gain
Budget and demonstration Token total is missing or above 14 with no correction Token total is at or under 14 but is not itemized Token total is at or under 14, itemized, and the demonstration shows one test row Budget is itemized and the team explains a trade it made, such as spending on the joint instead of the handle

Differentiation

Support

Give these teams a starter kit with the handle and the cup holder already joined, so the build begins at the part most likely to fail. Provide a test sheet with the columns filled in and the first row modeled. Shorten the reach target to 3 feet for sessions 2 and 3 and raise it to 4 feet only in session 4, so early tries end in a measurable result rather than a miss.

Extension

Ask these teams to add a fifth target of their own choosing and design to it, such as collecting the sample from 6 inches below the surface instead of at the top, which is closer to how real crews sample a stream. They should explain what changes in the tool when the cup has to go under and come back up closed, and test at least one way to keep surface scum out of the cup.

ELL supports

Label a full-size drawing of the pole with handle, joint, cup holder, and reach, and tape it where teams can point to it while talking. Demonstrate one full dip-and-return silently before any reading, then again while naming each part. Accept test-sheet entries written as numbers plus a sketch of what went wrong, and let the session 4 demonstration be mostly shown rather than spoken, with three labeled cards for the spoken part.

Extensions

Show students photographs of the extension samplers real monitoring crews carry and ask which parts of their own poles match and which parts the real tool adds, such as a bottle clamp that can be opened from the handle. Connect the work to why the sample has to come from moving water in the middle of the channel rather than from the quiet edge, and ask what that requirement would change about a pole built for a much wider creek.