Worksheet Grade 6 Engineering & Design

Foxglen Road Culvert Capacity and Peak Flow Worksheet

Nine items where students test three fictional replacement culverts against a required peak flow and a project budget, then check a safety margin.

Objectives

  1. Students will identify which culvert options meet a stated peak-flow requirement.
  2. Students will check culvert options against a fixed project budget.
  3. Students will calculate the percent of a culvert's rated capacity that a required peak flow represents.

Vocabulary

Key words: culvert, peak flow, capacity, constraint

Teacher overview

Foxglen Road (a fictional road used for this worksheet) carries an aging culvert, a pipe that channels stormwater under the road, that engineers must replace with a properly sized option. This worksheet has students compare three replacement culverts against the road's required peak stormwater flow and a fixed project budget, then check the chosen design's margin against an even heavier storm, the same criteria-and-constraints reasoning a real culvert replacement requires.

Answer Key

  1. Answer: Pipes B and C. Pipe B (520 gpm) and Pipe C (700 gpm) both meet or exceed 480 gpm; Pipe A (300 gpm) does not.
  2. Answer: Pipe B. Pipe B costs $1,900, less than Pipe C's $2,600.
  3. Answer: Under by $300. $2,200 minus $1,900 equals $300 under budget.
  4. Answer: Over by $400. $2,600 minus $2,200 equals $400 over budget.
  5. Answer: Pipe B. It is the only option that both meets the 480 gpm flow requirement and fits within the $2,200 budget; Pipe A fails the flow requirement, and Pipe C exceeds the budget.
  6. Answer: 40 gallons per minute. 520 minus 480 equals 40 gpm.
  7. Answer: 92 percent. 480 divided by 520 equals 0.9231, which rounds to 92 percent.
  8. Answer: No. A 550 gallons-per-minute peak flow would exceed Pipe B's 520 gallons-per-minute capacity by 30 gallons per minute, so Pipe B would be undersized for that heavier storm.
  9. Answer: Pipe A's 300 gallons-per-minute capacity is well below the required 480 gallons-per-minute peak flow, so it would not carry the storm's water even though it costs the least; an engineer must first check that a design meets its required constraints, such as flow capacity, before comparing cost.

Differentiation

Support

Provide a printed comparison table with the flow-requirement column and budget column already highlighted, and let students check off each pipe as "meets" or "fails" for each requirement before calculating any dollar or percent figures.

Extension

Ask students to find the minimum flow capacity, in whole gallons per minute, that a fourth replacement pipe would need in order to leave at least a 100 gallons-per-minute safety margin above the 480 gallons-per-minute peak flow.

ELL supports

Provide a simple cross-section diagram of a culvert pipe under a road with water flowing through it, labeled with the words "capacity" and "peak flow." Allow students to show comparisons using a simple table of checkmarks and numbers rather than full sentences.

Extensions

Have students research, using a teacher-provided map or photo, whether their own school or neighborhood has a visible culvert or storm drain, and describe in writing what they think happens to that pipe's capacity during an unusually heavy storm.