Project Grade 11 Math

Varnwell's Pumping Schedule: Least Cost Under a Time-of-Use Tariff

A four-session grade 11 project where teams build an hourly tank balance, design a 24-hour pumping schedule under storage limits, and defend its cost to a board panel.

Objectives

  1. Students will build an hourly running balance of a storage tank from demand and pumping.
  2. Students will express storage and capacity limits as inequalities and test schedules against them.
  3. Students will compare the energy cost and the demand charge of competing schedules.

Vocabulary

Pump station
A pump station is a building full of powerful pumps that push water through pipes or lift it uphill. Pumps give water the extra push that gravity alone cannot provide.

Also: time-of-use tariff, demand charge, usable storage, running balance

Teacher overview

Electricity is one of the largest line items a water utility pays, and utilities that buy power on a time-of-use tariff can cut that bill substantially by moving their pumping into the cheap hours and letting storage carry the expensive ones. The catch is that storage is finite, so a schedule that avoids every costly hour will empty the tank before the evening peak ends. Over four sessions, teams design a 24-hour pumping schedule for the fictional Varnwell Water District that meets every hour's demand, keeps the Ulverby tank inside its limits, and costs as little as possible. The part teams most often mishandle is the demand charge, which is set once a month by the highest simultaneous draw rather than by total energy, so the saving from running both pumps to reach the cheap hours has to be weighed against a month of that charge rather than against a single day's energy bill.

Rubric

Score each criterion on the four levels below.

Criterion 4, exceeds 3, meets 2, approaching 1, beginning
Hourly balance All 24 rows are arithmetically correct, the running level follows from the row above, and the starting level is stated and justified. The balance is correct with one or two arithmetic slips that do not change the verdict on any limit. The table is built but the running level is recomputed inconsistently, or several rows do not follow from the row above. No usable running balance, or demand and pumping are not tracked hour by hour.
Constraints as inequalities The floor, the ceiling, and the end-of-day condition are each written correctly as inequalities and each is tested against the schedule at the hour where it binds. All three inequalities are written correctly and tested, with a minor gap in the testing. Some limits are stated in words only, or one inequality is missing or reversed. Limits are mentioned but never written mathematically or tested.
Cost analysis On-peak energy, off-peak energy, and the demand charge are computed separately and correctly, and the comparison between the two schedules is stated in dollars per month. All three cost pieces are computed with a small error, and the comparison is stated. Energy cost is computed but the demand charge is omitted or misapplied, or the two schedules are not compared. Costs are asserted without a calculation a reader can follow.
Argument and defense The minimum on-peak pumping is justified from the on-peak demand and the usable storage, the graph is labeled and readable, and the hot-day risk is answered with the team's own numbers. The justification is present and mostly correct, the graph is labeled, and the risk question is answered. The proposal claims the schedule is cheapest without supporting it, or the graph lacks labels. The presentation restates the schedule without explaining why it was chosen.

Differentiation

Support

Give these teams a partly built balance table for the fictional Varnwell day, with the demand column filled and the first six rows completed, so their work begins at the decision of when to pump. Provide the three inequalities already written, and let them evaluate two supplied schedules against the limits before designing one of their own.

Extension

Ask these teams to treat the fictional Ulverby tank size as a variable and find the smallest tank that would allow the district to avoid all on-peak pumping. Then have them compare the yearly saving from that change against a construction cost the team estimates from research and labels as a fictional figure, and report whether the larger tank pays for itself.

ELL supports

Pre-teach "demand," "peak hours," "storage," and "demand charge" with a labeled drawing of a pump station filling a tank while houses draw from it. Provide a schedule table template with the column headings already written, and presentation sentence frames such as "We pump ___ pumps during hours ___ because ___," and "Our monthly cost is ___, which is ___ than the schedule we rejected."

Extensions

Teams can extend the fictional Varnwell schedule across a seven-day week in which weekend demand runs lower, and report whether the cheapest weekday schedule stays cheapest. A second task is to describe how a district would verify its own hourly demand in practice, and why a schedule built on a single day's table carries risk.