A six-session grade 11 project in which teams size a stream crossing that passes the design storm, restores trout passage, and fits a fixed budget and closure window.

Objectives

  1. Students will convert a design storm flow into a required structure opening area.
  2. Students will score four crossing alternatives against weighted criteria.
  3. Students will produce a dimensioned design that meets a budget and a closure limit.

Vocabulary

Key words: bankfull width, perched outlet, design storm, headwater, stream simulation

Teacher overview

Teams of three act as a design consultant to a fictional township that must replace a failing stream crossing under a rural road. The driving question is how to build one structure that carries the design storm without flooding the road, lets trout move upstream again, fits the money the township has, and closes the road for no longer than the school bus route can tolerate. The final deliverable is a design memorandum with a dimensioned cross-section, an alternatives matrix, a construction sequence, and a cost estimate, presented to a fictional township board. The misconception this project is built to correct is the belief that a culvert is adequate as long as it carries the flow, since the perched outlet that blocks fish is usually created by a pipe that passes water perfectly well but sits above the streambed, and a smooth pipe can run too fast for fish at the very flows that look successful on paper.

Rubric

Criterion 4, exemplary 3, proficient 2, developing 1, beginning
Hydraulic sizing and evidence Required area and minimum span are computed correctly with units shown throughout, and the trial section is checked against both independently Both calculations are correct with minor unit or rounding lapses, and the section satisfies both requirements One calculation is correct while the other is missing, assumed, or applied to the wrong dimension Sizing is asserted without calculation, or the section does not satisfy either requirement
Fish passage and habitat continuity The design removes the perched outlet, embeds the bed at a stated depth, keeps velocity within the limit, and explains how each choice serves passage The design removes the perch and embeds the bed, and velocity is within the limit, with explanation given for most choices Passage is addressed in general terms, with the perch removed but bed continuity or velocity left unresolved The design carries flow but leaves the outlet perched or the bed interrupted
Constraint management Cost and closure schedule are both within limits, and the memorandum states what was traded away to hold them One limit is met and the other is exceeded by a stated amount with a documented reason Both limits are addressed but at least one is exceeded without acknowledgment Cost or closure is not estimated at all
Communication to the board Drawings are dimensioned and readable, the matrix weights are justified, and the closing recommendation is clear to a non-engineer Drawings and matrix are complete and mostly clear, with some technical language left unexplained Drawings or matrix are incomplete, and the recommendation relies on jargon Deliverables are fragmentary and the recommendation is absent or unsupported

Differentiation

Support

Give these teams the required flow area already computed for the fictional site, with the calculation shown, so their Session 2 work begins at the trial section rather than at the arithmetic. Provide a partially weighted alternatives matrix with two criteria filled in, and supply a labeled example cross-section from a different crossing to model what a dimensioned drawing looks like.

Extension

Ask these teams to add a fifth alternative of their own to the fictional matrix and to defend its inclusion, then to test their recommended design against a storm larger than the one the township specified and report at what flow the road would overtop. A second task is to estimate the twenty-year maintenance cost of each shortlisted alternative and argue whether the cheapest structure to build is the cheapest to own.

ELL supports

Provide a labeled site diagram of the fictional crossing naming inlet, outlet, invert, streambed, headwater, and road shoulder, and post the same vocabulary with icons on the wall for the whole project. Allow the Session 1 brief to be submitted as a labeled table rather than prose, and offer presentation sentence frames such as "We recommend the ___ because it meets ___ while the others do not."

Extensions

Have students, under adult supervision and staying off the road and out of the water, locate a road-stream crossing near the school, photograph it, and classify it as passable or perched using the criteria from the fictional project. A second step is to compare their design against a published stream-simulation design guide from a state transportation or fisheries agency and to note which requirement in the guide the class project left out. Teams that want a physical model can build a scale flume from a plastic gutter, run water through a perched outlet and an embedded outlet, and record the difference in the drop a fish would face.