Project Grade 6 Engineering & Design

A Phased Water Plan for the Gossett Ridge Homes

Teams take three water-sector roles and design a two-phase plan for a fictional hillside neighborhood, since the grant pays for only part of the work they want to build.

Objectives

  1. Students will write measurable criteria and constraints from a client's goals for a water service problem.
  2. Students will design a phase-one package that fits a fixed budget and a fixed deadline.
  3. Students will state plainly which problems their phase-one package leaves unsolved.

Vocabulary

Service line
A service line is the small pipe that connects the water main under the street to the plumbing inside one home or building. It is the last leg of the trip water makes to your tap.

Also: water district, community well, phase, constraint

Teacher overview

Gossett Ridge is a fictional neighborhood of forty homes whose private wells are running dry and testing badly, and the fictional Tulloway Valley Water District has a grant that pays for less than half of what full service would cost. The design problem is therefore not which single solution is best but which part of the work should be built first, and what the neighborhood will still be living with afterward. Teams of three take the roles of a design engineer, a treatment operator, and a rate analyst, assemble two possible first phases from a shared parts list, choose one, and present a phased plan to a mock district board. The final deliverable is a four-page proposal that includes a page naming the problems phase one does not fix.

Rubric

Criterion 4, exceeds 3, meets 2, approaching 1, beginning
Criteria and constraints All four goals are rewritten as measurable criteria, all four constraints are named, and the ranking of goals is argued from the problem. All four goals are rewritten as criteria and all four constraints are named. Some goals stay vague, or one constraint is missing. Goals are copied without change and constraints are not separated from them.
Phase one fits its limits The cost table stays under the grant with a stated cushion, the two-year deadline is shown as a schedule, and the operator rule is addressed. The cost table stays under the grant and the plan fits the deadline. The table is close to the limit but unchecked, or the deadline is not addressed. Phase one exceeds the grant, or no cost table appears.
Two packages compared Both packages are scored on every criterion and the losing package is refuted point by point. Both packages are scored and the losing one is refuted on at least one criterion. Only one package appears, or the reason given is preference rather than a criterion. No comparison is made.
Honesty about phase one The page names each unsolved problem, says which homes it affects, and proposes an interim step for each. The page names the unsolved problems clearly. The page is vague, or it claims phase one solves more than the plan supports. The page is missing, or phase one is presented as complete service.

Differentiation

Support

Give these teams a parts list with a short picture beside each part, and a phase-one cost table with the row labels already written. Supply one worked example of a package built from two parts so the assembly step is modeled before they build their own.

Extension

Ask the team to add a phase-three section for the twenty-year horizon, and to name two measurements the district should take in the first year of phase one to find out whether the plan is working as promised.

ELL supports

Provide a role card for each of the three jobs with the tasks written as short steps, and a picture glossary for main, booster pump, well, and service line. Allow the presentation to be given from a labeled poster, and let a partner restate each board question before the student answers it.

Extensions

Invite a staff member from a local water utility or public works department to sit on the board panel, and ask them afterward to describe a project their own agency had to build in phases because the money arrived in pieces.