Lab / experiment Grade 6 Engineering & Design

Testing Three Pipe Bedding Materials for Oskett Lane

Students load a model pipe on soil, sand, and pea gravel, then measure settling, drainage, and soil movement to pick the bedding a fictional water main job needs.

Objectives

  1. Students will measure how far a loaded model pipe settles into three bedding materials.
  2. Students will time drainage and measure how far surface soil moves into each bedding.
  3. Students will select the bedding that satisfies all three job rules and propose a fix for one that fails.

Vocabulary

Key words: bedding, settlement, drainage, fines, trade-off

Teacher overview

A buried water pipe does not rest on the bottom of the trench. It sits on a layer of chosen material called bedding, which spreads the weight of the soil above it and lets water drain away from the pipe. Crews choose that material, and the choice pulls in two directions at once: loose open material drains quickly but lets fine soil wash down into its gaps, while tight material holds soil out but drains slowly and lets the pipe settle. In this lab students test three common bedding materials against three rules written for a fictional water main job on Oskett Lane.

Answer Key

  1. Answer: 9 mm.
    8 plus 10 is 18, and 18 divided by 2 is 9.
  2. Answer: 5 mm.
    4 plus 6 is 10, and 10 divided by 2 is 5.
  3. Answer: 4 mm.
    9 mm minus 5 mm leaves 4 mm.
  4. Answer: 2 beddings.
    Sand at 5 mm and pea gravel at 2 mm are both at or under 6 mm. Garden soil at 9 mm is over.
  5. Answer: 2 beddings.
    Sand at 60 seconds and pea gravel at 15 seconds are both at or under 90 seconds. Garden soil at 240 seconds is far over.
  6. Answer: 2 beddings.
    Garden soil at 0 mm and sand at 1 mm are both at or under 3 mm. Pea gravel at 6 mm is over.
  7. Answer: Sand.
    Sand settles 5 mm, which clears Rule 1, drains in 60 seconds, which clears Rule 2, and lets soil move only 1 mm, which clears Rule 3. Garden soil fails Rules 1 and 2, and pea gravel fails Rule 3.
  8. Answer: 4 times.
    240 seconds divided by 60 seconds is 4.
  9. Answer: The large gaps that let water through also let soil through.
    Accept any answer connecting the size of the spaces between the stones to both results: wide gaps drain quickly and give fine soil room to wash down into them. Accept students who add that soil filling those gaps would slow the drainage later.
  10. Answer: Answers vary.
    Accept any change that keeps the gravel but blocks soil from entering, such as wrapping the gravel in landscape fabric, laying a thin sand layer over the gravel, or capping the trench with packed soil. Strong answers cite the 6 mm soil movement reading as the result that needs fixing, and note that sand's 1 mm reading shows a finer material can hold soil back.

Differentiation

Support

Set up the three tubs before class and run the garden soil trials as a whole-class demonstration, so these groups begin at the sand tub with one row of the table already filled. Give them a ruler with the first 10 millimeters shaded to make the settling reading easier.

Extension

Have groups build and test the fix they proposed in item 10, measure the drain time and the soil movement again, and report whether the fixed gravel now passes all three rules.

ELL supports

Provide a labeled cross-section drawing of a trench showing the pipe, the bedding below it, and the soil above it, with an arrow for water draining away. Post the words "bedding," "settle," "drain," and "gap" with a small picture beside each. Allow items 9 and 10 to be answered with a labeled sketch and one sentence.

Extensions

Have students watch for an open utility trench in their community, sketch what they can see from the sidewalk, and write a short paragraph on whether the material under the pipe looks like the native soil or like something trucked in.